Bell Slope
YearOperation NameNumberTypeOpeningDistrictCityCountyCompany NameRailroad Shipments (tons)Railroad to MineTruck Shipments (tons)Total Production (tons)Days WorkedEmployeesNotes
1944Bell Slope Mine2 LackawannaBell Slope Coal Co.3,4586104,0682699 
1945Bell Slope Mine2 LackawannaBell Slope Coal Co.3,7011,9075,6082649Run of mine coal.
1946Bell Slope Mine2Jessup 2LackawannaBell Slope Coal Co.3,0153353,3502546Coal prepared at Moosic Mountain Breaker.

Note 2: From a list of Anthracite Operators. This may not be the operation location.